Q2 FY27 earnings call · November 06, 2026

Cemindia Projects Q2 FY27 Earnings Call: Order Book Hits Record Rs. 32,715 Cr, Reaffirms 20-25% Revenue Growth (CEMPRO)

Cofacto ResearchPublished November 06, 20268 min read
Listen to the earnings call
Quick summary

Cemindia Projects Ltd held its Q2 FY27 earnings call on November 05, 2026. Here's a quick read of what management said — performance, strategy, and the outlook ahead.

Strong Top Line, Margin Compression Persists

  • Q2 FY 2026-2027 revenue of Rs.2,749 crore — up 25% YoY from Rs.2,195 crore in Q2 FY 2025-2026; EBITDA rose 15% YoY to Rs.280 crore, with margin at 10.2% vs 11.1% in Q2 FY 2025-2026; PAT grew 21% YoY to Rs.131 crore.
  • H1 FY 2026-2027 revenue of Rs.5,470 crore — up 15% YoY; EBITDA margin at 10.3% vs 10.6% in H1 FY 2025-2026; PAT up 10.8% YoY to Rs.271 crore.
  • Q2 margin ex-other income at 9.7% — management reaffirmed FY 2026-2027 full-year margin guidance of 10%+ ("around 10% on an average throughout the year") versus the analyst's 10.5% question, while cautioning that certification delays and delayed execution starts keep margins "always a challenge."
  • Q2 revenue up ~1% QoQ vs Q1 FY 2026-2027 — better than the typical seasonal pattern where Q2 runs 10-15% below Q1; management suggested a work-mix effect (less monsoon-affected road work in FY 2026-2027) but did not confirm a ramp-up of end-FY26 order wins as the driver.
  • Balance sheet as of 30 September 2026 — net worth Rs.2,619 crore, net debt Rs.773 crore (net debt-to-equity ~0.3x); ROE 27%, ROCE 33%, working capital 96 days, H1 FY 2026-2027 capex Rs.150 crore.
  • Arbitration win of ~Rs.85 crore — additional claim payment received at Udhangudi in Q2 FY 2026-2027.

Record Rs.32,715 Cr Book; FY27 Inflow Target Set to Be Exceeded

  • Order book at all-time high of Rs.32,715 crore — vs a typical Rs.20,000-21,000 crore; ~Rs.15,000 crore of orders secured in H1 FY 2026-2027; management expects the FY 2026-2027 order inflow target of Rs.25,000 crore will "definitely be achieved and possibly exceeded."
  • Rs.5,968 crore of new orders since start of Q2 FY 2026-2027 — Rs.3,487 crore in Q2 plus Rs.2,481 crore in October 2026; Q2 inflows included a ~Rs.1,000 crore data center order in Andhra Pradesh from the group company, Damla Port ~Rs.800 crore, Project Varsa Outer Harbour for the Indian Navy ~Rs.700 crore, and a Rs.231.35 crore JSW contract.
  • October 2026 (Q3 FY 2026-2027) inflows of ~Rs.2,400 crore — Jaipur Metro Rs.781 crore, K-Ride Bangalore Rs.660 crore, and a Rs.1,000+ crore job at Dhubri, Assam from the group company; no tenders currently at L1 stage.
  • Bid pipeline of ~Rs.1,30,000 crore (Rs.1.38 lakh crore cited) — entirely external: marine ~Rs.25,000 crore, road/rail tunnels Rs.25,000 crore, underground metro Rs.6,000 crore, PSP Rs.10,000 crore, elevated metro ~Rs.5,000 crore; nuclear ~Rs.1,25,000 crore also cited; internal/group pipeline is additional and unquantified.
  • Group concentration is high — group entities account for 53-54% of the order book (Q2 FY 2026-2027) and contributed 70+% of order inflows over the trailing two-three quarters; H1 FY 2026-2027 revenue split was ~35-36% group, with management expecting the mix to gradually converge toward the order book composition.
  • Execution progress — Badawan Port work restarted after ~1.5 years of no progress; CMRL and Bangalore Metro at verge of completion; Ulangudi handed over; Bangladesh project substantially completed with payment received; ADNOC job in Abu Dhabi progressing well; Pune Metro and Delhi Metro commenced.

New Segment Scaling, But Revenue and Margin Profiles Still Unproven

  • Data center is ~15% of order book value — as of 30 September 2026 (Q2 FY 2026-2027); work in hand close to Rs.5,000-6,000 crore, with management pursuing additional group opportunities beyond Mumbai (including Gujarat).
  • ~6 data centers under execution — 2 at Vizag and 4 at other locations, plus a few more just started in Gujarat; precast completed up to 8 of 10 storeys on the first two, with MEP vendors nearly finalized and orders placed.
  • Revenue ramp hinges on MEP scaling — civil works are ~20% of project value with the electromechanical package at ~80%; civil execution spans 18-24 months, erection of the first data centers expected to start January-February 2027, and the CFO guided to MEP-driven revenue traction in Q4 FY 2026-2027.
  • Data center margins expected not to exceed 10% (period unspecified) — within the company's typical segment margin range of 8-13%; underground and marine segments command better margins; management declined to predict the segment's margin profile until execution trends are visible.
  • MD Jayanta Basu said volumes will grow "quite substantially" — given strong daily inquiry flow, but the company will initially confine itself to data center jobs within group activity; no quantified revenue contribution or incremental inflow guidance was disclosed.

Rs.1,400 Cr Raise Funds a Shift to Rs.10,000 Cr-Plus Projects

  • Rs.1,400 crore QIP completed in October 2026 (FY 2026-2027) — 1.26 crore shares issued at Rs.1,108 per share; bids of ~2.3x the Rs.1,000 crore base deal size from domestic mutual funds and other financial investors; proceeds earmarked for capex, repayment of certain borrowings, working capital, and general corporate purposes.
  • Management is pursuing big-ticket projects of Rs.10,000 crore plus — which attract limited competition and can deliver good margins with the right technique and job knowledge; the company has progressed from Rs.20-40 crore jobs to Rs.1,000 crore-scale projects and now targets Rs.3,000-4,000 crore-plus jobs (FY 2026-2027).
  • Further capex of Rs.150-200 crore guided for the remainder of FY 2026-2027 — on top of Rs.150 crore in H1; if a large-diameter TBM job is secured, incremental capex "can go up to another Rs.1,500 crores," with CFO Nitesh Sharma confirming the major chunk would fall in FY 2027-2028 given 14-16 months of TBM deployment lead time.
  • TBM supply risk downplayed — MD Jayanta Basu stated "China cannot stop us doing business"; TBMs can be sourced from countries other than China, which Cemindia is pursuing; at least 4 other TBM tenders are being closely worked on beyond the Bangalore job, with "very likely chances" at least one is won (timeline unspecified).
  • ROE dilution acknowledged — CD Research's Nipur Kemka estimated ROE may fall to ~17% in FY 2027-2028 from 28% in FY 2025-2026; MD Jayanta Basu said the company has to "live with" near-term dilution as a short-term-vs-long-term trade-off; CFO indicated scale-up may resume post 24 months (from ~FY 2028-2029 onwards) once large machines begin contributing.
  • Rs.5,000 crore enabling approval is "just an enabling one" — CFO clarified it is not an imminent dilution; a prudent funding call will be taken based on pipeline conversion, with enough balance-sheet headroom to raise leverage.

Rs.50,000 Cr Addressable Within Group Capex; No L2 Price-Matching

  • Citing the Adani Group's committed capex of close to Rs.2 lakh crore every year for the next 5 years — analyst Sunil Shah asked about the addressable opportunity; MD Jayanta Basu estimated around Rs.50,000 crore of this planned capex is addressable for Cemindia.
  • MD Jayanta Basu confirmed total potential of close to Rs.1,30,000 crore — from business outside the group (period unspecified) plus the Rs.50,000 crore addressable within the Adani Group.
  • Port business order book stands at Rs.7,500 crore — of which Rs.1,500 crore pertains to Wadhwan Port (position as of Q2 FY 2026-2027, confirmed by MD Jayanta Basu and CFO Nitesh Sharma).
  • No PSU-style L2 price-matching mechanism exists within the Adani Group — MD clarified each Adani company has its own management protecting its business interests, work is awarded via competitive bidding, and such price-matching "has not happened ever so far."
  • Adani tunnel order remains uncertain — MD declined to comment on whether the order will be awarded to the Adani group ("neither I am bidding the job, neither I am giving the job"), but stated there is a "high possibility" Cemindia gets the job if the group wins; no award timeline was provided; funds can be redeployed across 6-7 pipeline jobs if it does not materialize.
  • New Bombay Phase 2 in advanced discussions — Adani is in advanced discussions with prospective bidders, with Cemindia among them; management hopes work will start by Q3 or Q4 FY 2026-2027.

FY27 Guidance Held; Growth Payback Skewed to FY28

  • FY 2026-2027 revenue growth guidance maintained at 20-25% — reaffirmed by management on the Q2 call; MD Jayanta Basu said the effect of work in hand and work expected will come through in FY 2027-2028, with no much incremental benefit expected in FY 2026-2027; H1 guidance (revenue and margin) maintained.
  • CFO guided to at least a 25% top-line CAGR over the next three years — FY 2027-2028 through FY 2029-2030, responding to a question citing top-line growth from Rs.5,000 crore to Rs.10,000 crore over the last 4-5 years.
  • Margin bridge hinges on new jobs converting — recent dilution attributed to jobs not yet reaching the threshold limit to declare margin, including Vadhavan Port; newly secured jobs (Munger, K-Ride, DMRC Pune) will convert to margin after one or two quarters, i.e., around Q4 FY 2026-2027 to Q1 FY 2027-2028.
  • Wadhwan Port: construction has started, but no revenue guidance — management declined to provide a revenue-contribution timeline or revenue potential, stating it would "not be fair" to give revenue guidelines at this stage and that execution pace "needs to be seen."
  • Mechanization over manpower — MD contrasted a Rs.1,500 crore building job requiring ~2,500 laborers versus ~500 for a Rs.1,500 crore underground metro; management consciously avoids labor-intensive segments and is prioritizing mechanized jobs and technology upgrades, alongside expanding from 4-5 to 7-8 divisions with capable leaders.
  • No quantified incremental ROCE or cash generation targets were provided for the 3-5 year horizon raised by the analyst; management committed only that QIP proceeds will be "prudently used for the company's benefit."

Ask about this

Ask Cofacto a question about this call. Answers cite filings and company data.