Q2 FY27 earnings call · November 16, 2026

Godawari Power & Ispat Ltd (GPIL) Q2 FY27 Earnings Call: Cuts Iron Ore Guidance To 2.5 MT, Sees Margin Normalisation From Q1 FY28

Cofacto ResearchPublished November 16, 20268 min read
Quick summary

Godawari Power & Ispat Ltd held its Q2 FY27 earnings call on November 13, 2026. Here's a quick read of what management said — performance, strategy, and the outlook ahead.

Strong Top Line, Compressed Margins

  • Revenue up 25% YoY to Rs.1,632 Cr in Q2 FY27 — and 29% YoY to Rs.3,382 Cr in H1 FY27, per CFO Sanjay Bothra, on healthy sales volumes and improved realisation.
  • Margins compressed sharply — Q2 FY27 EBITDA margin of 12.12% and PAT margin of 5.2%, versus H1 FY27 EBITDA margin of 15.7% and PAT margin of 9.1%; Q2 declined QoQ on lower pellet realisation.
  • Cost headwinds from market-sourced iron ore and coal — H1 FY27 profitability pressured by elevated ore costs and higher coal prices amid the West Asia crisis.
  • Production guidance cut for FY27 — iron ore mining lowered from 3.4 million to 2.5 million tonnes, pellet production from 4.4 million to 3.5 million tonnes; ferroalloys and sponge iron each above 50% of annual targets.
  • Overburden dumping space constrained mining — Abhishek Agarwal clarified the constraint affects both current and expanded capacity, not just newer capacity; a 2 million tonne pellet plant was also temporarily closed for uneconomical operations.
  • Steel chain ex-pellets performing well — billets commanding a healthy premium since PGIL approval; steel melting shop capacity expanded from 5.25 lakh to 5.75 lakh MT, in commercial production from Q2 FY27, enabling almost 100% captive sponge iron use in billets.

Tree-Cutting Clearance Is the Pivot Point

  • Tree-cutting approval expected imminently — Abhishek Agarwal said it was expected "anytime soon this week," with all clearances by Q3 FY27 and land use starting from 2 December 2026; he declined to share official documentation on the permission status.
  • Mining ramp-up is gradual — only slight improvement in Q4 FY27 due to site infrastructure needs; 70-80% of mining capacity expected from Q1 FY28 onwards, and "from October 27, we should be able to start mining at 6 million capacity after the monsoon gets over."
  • External ore purchases phase down — roughly 2 million tons bought from the market in full-year FY27 (about 0.7-0.8 million tons external in H2 FY27), falling to about 0.5 million tons in FY28 at 80-85% capacity (~5.2 million tons); management expects to be "100% captive" from FY 2028-2029 onwards.
  • Ari Dongri reserves — about 80% of exploration complete; reserves could rise modestly from 80 million tons to 90-95 million tons, with 80 million tons treated as the base case for 15 years at full capacity.
  • Boradipoo expansion — current capacity 0.7 million tons (full operation from FY28), targeted to reach 4 million tons by FY31 with TOR filing and environmental clearance underway; ~75 million tons of reserves are low grade, with a 4 million ton beneficiation plant yielding ~1.5 million tons/year at 40% recovery.
  • Pellet margin recovery tied to captive ore — pellets sold from purchased fines currently earn only Rs.500-700 per ton EBITDA; at a Rs.10,000 price and full mining capacity, Agarwal said pellet EBITDA would be more than Rs.4,000 per ton (~50% margin vs. production cost of Rs.5,500-6,000 per ton).

Quantifying the Q2 Erosion

  • Market iron ore fines added Rs.3,000-3,500 per tonne to costs on a yearly average, while high-grade pellets sold at less than Rs.1,000 per tonne margin — a "substantial loss" per Abhishek Agarwal.
  • Coal and power costs rose on the war — DRI coal up Rs.1,000-1,500 per tonne and power up Rs.0.50-0.75 per unit; DRI coal impact quantified at ~Rs.15 Cr for the quarter, with about Rs.25-30 Cr lost in Q2 FY27 attributed to rising coal costs.
  • Product prices rose in parallel — billet moved from ~Rs.36,000-38,000 to Rs.43,000 and DRI from Rs.24,000 to Rs.29,000; Agarwal said the remaining cost increases were not a straight-away EBITDA loss, while the pellet impact was.
  • High-grade pellet merchant sales at zero — previously 50,000-1 lakh tons per period at a Rs.1,000/ton premium; resumption expected from Q4 FY27 as mining ramps up, a Rs.1,000/ton realisation headwind in the interim.
  • Pellet price volatility — prices moved from ~Rs.8,500/ton (end Q1/early Q2 FY27) to ~Rs.11,500, now back at ~Rs.10,500/ton; Agarwal sees a sustainable band of Rs.9,500-10,500 per tonne ex-Raipur over the next 6-8 months.
  • Margin trajectory guided — Q3 FY27 margins similar to Q2, marginal improvement in Q4 FY27, and normalised levels from Q1 FY28 onwards, contingent on regulatory permission for overburden dumping land and beneficiation plant commissioning.
  • Long-term margin guidance corrected — after analyst Varun Mehta flagged a discrepancy between the annual report's 12-13% and an earlier call's 7-8%, Dinesh Gandhi said the longer-term best margin should be 5-7%, citing high volume turnover.

Battery Storage and CRM Execution

  • 20 GW BESS project "very much on track" — first lot dispatched from China after testing in FY27; first container expected "by end of Q1, early Q2, which is June, July of 27" (FY28), with commissioning expected by June-July FY28.
  • BESS economics outlined — on ~Rs.1,400 Cr investment, Agarwal cited turnover of ~Rs.13,000 Cr at 80% capacity of 15 GW, a 5% EBITDA margin (~Rs.600 Cr annual EBITDA at full capacity), and payback of at most 3-3.5 years including ramp-up.
  • New 3 GW line for smaller containers — 260 kWh and 418 kWh units for C&I users; machine supply begins July-August FY28, commissioned by December FY28; 10-20% utilisation guided in the first year, reaching at least 20-25% by March FY28.
  • Tender strategy via new EPC arm — Godawari Energy Solutions Limited formed to bid; bidding started but no tender won yet; 90-95% of BESS demand comes from government tenders (SECI, Coal India, NTPC, state discoms); company aims to create its own consumption of 40-50% of the 20 GW capacity, though no decision made on investing in asset creation.
  • Cell technology upgrades — 628 cells under the Chinese supplier agreement, expected to deliver at least 4-5% operating cost savings and ~1.5% additional EBITDA on the 5 MW container; tender criterion is 20% DCR content by value, which the company qualifies for.
  • CRM complex in Maharashtra — mega status policy signed with the Maharashtra government worth Rs.1,000 Cr, including a 9% SGST refund on in-state sales; site work started after Diwali, commissioning envisaged for December 27, possibly stretching to March 28 (FY28).
  • Competitive context — Agarwal acknowledged new capacity announcements in the last 6 months are "alarming" on paper, but noted execution takes 18-24 months, giving GPIL a first-mover advantage "for at least next couple of years" from FY27.

Large Commitments, Ample Sanctioned Lines

  • Rs.2,795 Cr in credit facilities sanctioned — Dinesh Gandhi clarified ~Rs.1,995 Cr is non-funded, with funded facilities of only ~Rs.800 Cr, including a Rs.700 Cr term loan for the base project and Rs.100 Cr working capital.
  • Capex commitments across three verticals — Rs.100 Cr from internal accruals for a container manufacturing line at the CRM complex (commissioning by March 2027, FY27), Rs.135 Cr for a small-capacity battery storage project (by March 2028, FY28), and Rs.100 Cr for 50 EV dumpers.
  • Liquidity position — CFO Sanjay Bothra cited ~Rs.900 Cr of free cash, ~Rs.500 Cr being tied up against the CRM project, and said the company does not foresee any cash crunches; all projects on track with no execution delays from cash deployment.
  • Intercorporate loans being called back — ~Rs.120 Cr lent at 12-15% interest, to be written back within the next 9-12 months (during FY28), given huge capex plans; no further intercorporate lending afterwards.
  • Captive power expansion — from 190 MW to 290 MW; the 100 MW solar project now expected by December 2026 after a delay of a couple of months; Rs.26 Cr invested for a 26% stake in Solar Craft Power India 32 Limited for a 50 MW group captive solar project.
  • Beneficiation plant timeline — targeted for commissioning in Q3 FY27, ramp-up from Q4 FY27, and full-scale operations by FY28.

Recovery Hinges on Mining Ramp and Ore Prices

  • Substantial pellet volume jump expected — Agarwal expects all pellet plants at full capacity with a "substantial jump in pellet volumes from Q1 FY 2027-2028 onwards," though some external ore sourcing continues in H1 FY28.
  • Iron ore prices near-term stable — around $90-92 per tonne in early November 2026, expected to average ~$90/tonne near term, with downside risk from incremental low-cost supply including the Simandou ramp-up.
  • Domestic demand supportive — per management, crude steel production grew 2.9% YoY and finished steel consumption grew 7.6% YoY in H1 FY27; Agarwal also noted India's steel production growing 10-12% every year, implying rising iron ore imports that he said will not affect domestic pellet prices.
  • Pellet overcapacity in some regions — supply rising as captive mine companies such as Lloyds add pellet capacity year on year; pressured prices in oversupplied regions.
  • Steel plant remains on hold — approvals still pending, especially on the water side; the desired approval has not yet been obtained.
  • Vision reiterated — management reiterated its Vision 2013 target of 4x revenue growth and 3x EBITDA and PAT growth.

Ask about this

Ask Cofacto a question about this call. Answers cite filings and company data.

Companies on this page

Related

Share on X · LinkedIn · WhatsApp

Disclaimer: This earnings call summary is published for educational and informational purposes only. It is not investment advice, not a recommendation to buy, sell or hold any security.